Home / Buying / New Construction Guide

Buyer Guide

Buying a New Construction Home or Condo in Ontario

The whole process in plain language: every key date until closing, when you can back out, when you can rent or sell, and what selling before closing really costs. Freehold and condo, side by side.

The short version

When you buy a home that isn't built yet, you're signing a contract today for a home you'll get in one to five years. You pay deposits along the way, the builder builds, and you pay the rest on closing day. The biggest differences between a freehold home (detached, semi, freehold townhouse) and a condo are when you can back out, how closing works, and what you're allowed to do before you own it.

Your contract is binding

Outside a few specific exits, you can't just walk away. If you don't close, you can lose your entire deposit and be sued for the builder's resale loss.

The dates are in writing

Every Ontario builder contract has a Tarion Statement of Critical Dates. It tells you when the builder expects to finish, how far they can push it, and when you can cancel.

Selling early is possible, with costs

Before closing you can only sell the contract (an "assignment"), and only if the builder agrees. Expect a builder fee, 13% HST on your profit, and possibly full income tax on it.

Freehold homeCondo
Cooling-off periodNone yet for agreements signed before Jan 1, 202810 days from when you receive all required documents
How many closingsOne. You get the keys and ownership the same dayTwo. Interim occupancy (you move in, pay a monthly fee) then final closing (you get ownership)
Deposit protectionTarion: up to $60,000 (homes $600,000 or less) or 10% of price up to $100,000. Register with Tarion within 45 days of signing to get the full amountHeld in trust by law, plus Tarion coverage up to $20,000
Typical deposit5% to 10%, paid over a few months15% to 20%, paid over one to two years
Rent it out before you own itNoMaybe during interim occupancy, only with the builder's written OK
Sell before you own itAssignment only, if the builder consentsAssignment only, if the builder consents (including during interim occupancy)

Step by step

The complete process, from signing to keys

  1. Day 1

    Sign the agreement of purchase and sale

    You pick a lot and model and sign the builder's agreement. Attached to it is the Tarion addendum with the Statement of Critical Dates. There's no legal cooling-off period for freehold homes yet, so ask the builder to add a clause giving your lawyer 7 to 10 days to review the agreement before it becomes firm.

  2. Within 45 days

    Register your purchase with Tarion

    Tell Tarion about your purchase within 45 days of signing. If you do, your deposit gets the maximum protection. If you're late or never do it, your deposit is still protected, but possibly for a lower amount.

  3. First months

    Pay your deposits

    Deposits are usually paid in a few instalments (for example, at signing, 30 days, 60 days and 90 days). Unlike condo deposits, freehold deposits don't have to be held in trust, which is why Tarion's protection and a financially solid builder matter.

  4. Months 3 to 12

    Choose colours and upgrades

    You'll book a décor appointment to choose finishes. Upgrades are usually paid upfront and add to the price. Get every choice and price in writing.

  5. During construction

    Watch for delay notices

    The builder can push the date back, but only within the limits in your Statement of Critical Dates and only with proper written notice (usually 90 days ahead). See the key dates section below.

  6. 60 to 90 days before

    Line up your mortgage

    Your lender approves you based on your income and the home's appraised value at closing, not when you signed. If prices have dropped, the appraisal can come in below your price and you'll need to cover the difference in cash.

  7. Before closing

    Pre-delivery inspection (PDI)

    You walk through the finished home with the builder and list anything damaged, incomplete or missing on the PDI form. This record matters for your warranty.

  8. Closing day

    Close and get your keys

    Your lawyer pays the balance, plus land transfer tax and closing adjustments (things like utility hookups, Tarion enrolment and development charge levies, depending on your contract). Your HST rebate is usually already credited in the price. Ownership and keys transfer the same day.

  9. After closing

    Warranty

    Tarion warranty coverage runs 1, 2 and 7 years. Submit the 30-day form in your first 30 days and the year-end form in the last 30 days of your first year.

Key dates

Every key date until closing

The first page of the Tarion addendum is the Statement of Critical Dates, signed by you and the builder. Here's what each date means in plain language. The builder can choose a firm date from day one, or start with a tentative date that it can move within these limits.

Freehold homes

DateWhat it means for you
First Tentative Closing DateWhen the builder expects to finish. Every other date is counted from this one. If the builder doesn't give you written notice of a delay at least 90 days before it, this date automatically becomes your firm closing date.
Second Tentative Closing DateThe builder can push closing back once, by up to 120 days, without paying you anything, as long as it gives 90 days' notice.
Firm Closing DateNo later than 240 days after the first tentative date. From here on, any further delay means the builder owes you delayed closing compensation.
Delayed Closing DateA new date the builder sets if it misses the firm date. You're paid $150 per day for living expenses (no receipts needed) plus other costs like moving and storage with receipts, up to $7,500 in total. If you get less than 10 days' notice of a delay, you get an extra $1,500.
Outside Closing DateThe absolute latest date: 365 days after the second tentative date or the firm date, whichever is earlier.
Purchaser's Termination PeriodIf the home isn't ready by the outside date, you have 30 days to cancel and get back everything you paid (deposits, upgrades and extras), plus interest and delay compensation.

Condos

DateWhat it means for you
First Tentative Occupancy DateThe builder's expected move-in date. The builder can move it, and can set more than one tentative date, as long as it gives at least 90 days' written notice each time and never goes past the outside date. Late notice turns the tentative date into the firm date.
Final Tentative Occupancy DateIf the current date can't be met, the builder must set this within 30 days of finishing the roof.
Firm Occupancy DateWith 90 days' notice, the builder can push the final tentative date once more, by up to 120 days. That becomes the firm date. After it, delays mean compensation for you.
Delayed Occupancy DateSet if the builder misses the firm date. Same compensation as freehold: $150 a day for living costs, other costs with receipts, up to $7,500 total, plus $1,500 if you get less than 10 days' notice.
Outside Occupancy DateA real calendar date agreed at signing. It's the latest the builder can give you occupancy.
Purchaser's Termination PeriodIf you can't move in by the outside date, you have 30 days to cancel and get all your money back, with interest.
Final closingNot in the Statement of Critical Dates. It happens after the building is registered, usually weeks to months after occupancy, sometimes more than a year.

Early termination conditions. The addendum can also let the builder cancel the whole deal if it doesn't get approvals, financing or enough sales by certain dates. If that happens, you get your deposit back with interest, but not the home. Check those dates before you sign, and check any amendment the builder asks you to sign later.

Backing out

When can you legally get out of the contract?

Once your agreement is firm, you can only cancel in specific situations. Here they are side by side.

SituationFreeholdCondo
Changed your mind soon after signingNo legal right for agreements signed before Jan 1, 2028, unless your contract has a lawyer-review or other condition. A 10-day cooling-off period applies to agreements signed on or after Jan 1, 2028.Yes, within 10 days of receiving the signed agreement, disclosure statement and Buyers' Guide. Full refund with interest.
A required document was never given to youDepends. Speak to a lawyer.Possibly. In 2026, an Ontario court ruled a condo agreement wasn't binding because the builder couldn't prove it gave the buyer the Buyers' Guide, and the buyer got the deposit back.
Big change to the projectUsually noYes, within 10 days of being told about a material change to the disclosure statement
Builder misses the outside dateYes, within 30 days after the Outside Closing DateYes, within 30 days after the Outside Occupancy Date
Your own condition isn't metYes, if your contract has one (for example, lawyer review or financing) and you cancel by its deadlineYes, same
Builder cancels the projectDeposit back with interestDeposit back with interest
You and the builder agreeA mutual release. The builder may ask you to give up part or all of your deposit.Same
You can't get a mortgage, or the appraisal comes in lowNoNo

What happens if you just don't close. That's a default. The builder can keep your whole deposit and sue you for the difference between your price and what it resells the home for, plus its carrying costs, commissions and legal fees. A low appraisal or a declined mortgage is not a legal excuse. If you think you might not be able to close, talk to a lawyer and a realtor early: an assignment or a negotiated release is almost always cheaper than a default.

Selling

Selling before or after closing, and what it costs you

Before closing: an assignment

Until closing, you don't own a home, you own a contract. To sell, you assign your contract to a new buyer (the "assignee"). They pay you back your deposits plus your profit, then close with the builder in your place. For a condo, this includes the interim occupancy period, because you still aren't the owner.

  • Builder consent: almost every contract needs the builder's written OK. Some builders ban assignments, only allow them after the project is sold out, or don't let you list on MLS.
  • Builder fee: often a few thousand dollars, sometimes more, plus HST, plus the builder's legal fees.
  • 13% HST on your profit: every assignment of a new home is taxable. HST applies to the profit, not the deposit you're getting back, as long as the agreement says how much is the deposit.
  • Income tax: if you assign within 365 days of signing, the profit is fully taxed as business income and a loss can't be claimed. After 365 days, the CRA may still treat it as business income if you bought to resell.
  • You may still be on the hook: under most builder contracts, you stay responsible if your buyer doesn't close.
  • Your profit may wait: part of your profit is sometimes held in trust until your buyer closes.
  • Your buyer's costs: they pay land transfer tax at closing on a value that may include the assignment price.

After closing: a regular sale

Once you own it (after closing for freehold, after final closing for a condo), you can list and sell it like any other home. No builder consent is needed, though some contracts restrict listing while the builder is still selling.

  • Sold within 365 days of closing: the profit is taxed as business income and you can't use the principal residence exemption. There are exceptions for life events like a death, a new child, a separation, a job loss or relocation, a serious illness or insolvency.
  • New-home HST rebates: the federal and Ontario rebates, including the first-time buyer and 2026 enhanced rebates, require that you (or a relative) are the first to live there as a primary residence. Selling or renting it instead of moving in can mean losing the rebate or having to repay it.
  • Mortgage penalty: breaking your mortgage early usually costs a prepayment penalty.
  • Commission and legal fees apply, as with any sale.
StageFreehold: can you sell?Condo: can you sell?
Cooling-off periodNo cooling-off yet (agreements before Jan 1, 2028)Cancel instead, with a full refund
During constructionAssignment, with builder consentAssignment, with builder consent
Interim occupancyNot applicableAssignment, with builder consent
Within 365 days after you own itYes. Profit is taxed as business income unless an exception appliesYes. Same tax rule, counted from final closing
After 365 daysYes. A home you lived in may be tax-free under the principal residence exemptionYes, same

Renting

When can you rent it out?

StageFreeholdCondo
Before closing / during constructionNo. Nothing to rent yetNo
Interim occupancyNot applicableOnly with the builder's written consent. The builder still owns the unit. Many contracts ban leasing during occupancy or charge a fee. Some ask you to give up delay compensation in exchange, so read carefully.
After closing / final closingYes. Follow your city's rental and second-unit rules, and tell your lender and insurerYes, subject to the condo's declaration and rules (many ban short-term rentals like Airbnb)

Renting changes your HST rebate. The standard new-home rebates assume you or a relative will live there. If you plan to rent it out, the builder will usually charge you the rebate amount on closing. You then apply to the CRA yourself for the new residential rental property rebate, which generally needs a lease of at least one year. Once you rent it out, the first-time buyer and 2026 enhanced rebates for owner-occupied homes don't apply.

Calculator

Assignment sale calculator

Thinking of selling your contract before closing? Enter your numbers to see what you'd actually keep after the builder's fee, commission, HST and income tax.

Your profit before costs is this minus your original price.
HST on the profit is
HST is added.
HST is added. Enter 0 if you're not using an agent.
Approximate Ontario combined rates.
Tax treatment
"Based on dates" applies the 365-day flipping rule. If you bought to resell, the CRA can treat any profit as business income.
What you keep after tax
$0

Estimates only, not tax or legal advice. They don't include mortgage, occupancy fee or carrying costs you've already paid, or any HST rebate you give up. Have an accountant and a real estate lawyer review any assignment before you sign.

Common questions

Quick answers

Is my deposit safe if the builder goes bankrupt?

Mostly. Condo deposits must be held in trust, and Tarion covers up to $20,000 if they weren't. Freehold deposits are covered by Tarion up to $60,000 (homes $600,000 or less) or 10% of the price up to $100,000. To get the full freehold coverage, register your purchase with Tarion within 45 days of signing.

Do I get a cooling-off period on a new freehold home?

Not yet. Ontario has passed a 10-day cooling-off period for new freehold homes, but it only applies to agreements signed on or after January 1, 2028. Until then, ask for a lawyer-review condition before you sign.

Can the builder raise the price after I sign?

Not the base price. But read the closing adjustments section of your contract: development charge increases, utility hookups and other items can add thousands at closing unless they're capped. Ask your lawyer to negotiate caps before you sign.

How much are condo occupancy fees?

Interest on your unpaid balance at the rate set by the rules, plus estimated monthly property tax and condo fees. Expect roughly what a mortgage payment plus condo fees and taxes would cost, but none of it goes toward your price.

What if the appraisal at closing is lower than my price?

You still have to close at the price you agreed. Your lender will only lend based on the appraised value, so you'll need to cover the gap in cash, find another lender, assign the contract, or negotiate with the builder. Start planning 90 days before closing.

Can a non-Canadian buy my assignment?

The federal ban on most non-Canadians buying homes in Canadian cities runs until at least January 1, 2027. Check the current rules before signing with a buyer who isn't a citizen or permanent resident. Ontario's 25% Non-Resident Speculation Tax may also apply.

Buying or Selling New Construction?

Mani can review a builder's agreement with you, explain your critical dates, and help you price and market an assignment.